System status on date: | 03/16/2016 | System Status: | Compliant |
Property Information
Property Information: | |||||||||||||||||
Owner's representative: |
|
Impact on Public Health
System discharges sewage to the ground surface: |
No | System discharges sewage to drain tile or surface waters: |
No | System causes sewage backup into dwelling or establishment: |
No |
Verification method(s): | Searched for surface outlet Searched for seeping in yard/backup into home Homeowner testimony (See Comments/Explanation) |
Tank Integrity
System consists of seepage pit, cesspool, drywell, or leaching pit: |
No |
Sewage tank(s) leak below their designed operating depth: |
No |
Verification method(s): | Probed tank(s) bottom Examined construction records |
Other Compliance Conditions
Maintenance hole covers are damaged, cracked, unsecured, or appear to be structurally unsound: |
No |
Other issues (electrical hazards, etc.) to immediately and adversely impact public health or safety: |
No |
System is non protective of groundwater for other conditions as determined by the inspector: |
No |
Date of Install
Date of install known: | Yes |
Date of installation: | 06/08/1985 |
Soil Separation
Shoreland/Wellhead Protection/Food, beverage, lodging? | No |
Drainfield has at least a two-foot vertical separation distance from periodically saturated soil or bedrock: |
Yes |
Drainfield meets the designed vertical separation distance from periodically saturated soil or bedrock.: |
No |
Verification method(s): | Conducted soil observation(s) (Attach boring logs) |
Comments/Explanation: | 0-8 top soil 10yr 3/2 8/17 fine silty loam 10yr 4/3 17-32 clay 7.5yr 4/4 32-74 clay loam 10yr 4/4 Redox @ 68" |
A. Bottom of distribution media: | 42 Decimal Feet |
B. Periodically saturated soil/bedrock: | 0 Decimal Feet |
C. System separation: | 24 Decimal Feet |
D. Required compliance separation: | 24 Decimal Feet |
Operating Permit and Nitrogen BMP
Is system operating under an Operating Permit: | No |
Is the system required to employ Nitrogen BMP: | No |
Comments and File Attachments
Comments or recommendations: | 1250 gallon septic tank, 1000gallon pump tank and pressure bed drainfield. Pressure bed drainfield 42" deep. Gravel has been installed over a portion of the drainfield for trailer parking. New riser installed on pump tank in spring of 2015. Old cesspool was disconnected and abandoned, but not removed and filled in. The cesspool is no longer in use and is dry. |
Attach Files: |
Certification
Inspector: |
|
Terms
Certification
By submitting this form I hereby certify that all the necessary information has been gathered to determine the compliance status of this system. No determination of the future
system performance has been nor can be made due to unknown conditions during system construction, possible abuse of the system, inadequate
maintenance, or future water usage
Invoice #701 (04/12/2016)
Charge | Cost | Quantity | Total |
---|---|---|---|
added 04/12/2016 3:30 PM $40 Flat Fee |
$40.00 | x 1 | $40.00 |
Grand Total | |||
Total | $40.00 | ||
Payment 04/12/2016 | $40.00 | ||
Due | $0.00 |
Action: Print
Approvals
Approval | Signature | Options |
---|---|---|
Applicant | Tom Trooien - 04/12/2016 3:31 PM - witnessed by Kati Hallermann 18c99b5808d39e7479afa165b56d7866 ef76af3142c96762805a977f6723e2c5 | |
#1 Compliance Inspection Accepted | Kati Hallermann - 04/12/2016 3:31 PM af17fc23742cdeb761bfd3eed230c583 59e4782a871974f809330634e19d677f |
Inspection has been approved. All signatures have been obtained.
Text: | |
File(s): |
Text: | |
File(s): |
Compliance Letter Type: | Who's signature should be on the letter? | Permit number to reference in "No Replace" letter: | |||
Was the letter sent? | Compliant/Non-Compliant: |
Certificate of Compliance: |
Letter of Non-Compliance: |